Reports 15
Logamax plus GB162-80 kW/100 kW - Subject to modifications resulting from technical improvements! 85
15 Reports
15.1 Start-up report
z Enter your signature and the date after completing the start-up activities.
Start-up activities Page Measurement results Remarks
1. Check for gas leaks 46
2. Fill the heating system 47
– Pre-pressure expansion vessel (refer to the installation
instructions for the expansion vessel)
____________ psi
– Heating system filling pressure ____________ psi
3. Fill the condensate trap with water 48
4. Write down the gas characteristics: Heat input ____________ btu/ft³
Heat output ____________ btu/ft³
5. Bleed the gas supply valve 49
6. Check the air/flue gas connection 49
7. Checking the appliance configuration 50
8. Measure the gas inlet pressure (working pressure) 50 ____________ inch W.C.
9. Check and adjust the gas/air ratio 52 ____________ inch W.C.
10. Carry out a leakage test in operating conditions 54
11. Measure the flue gases CO emissions 55 ____________ ppm
12. Carry out a function test 56
- Measure the ionization current 56 ____________ μA
12. Measure the pH-value Fill in the record book
13. Boiler settings 58
14. Final activities 60
- Close the boiler door and the control panel
- Hand over
Confirming proper start-up
Company stamp/signature/date