2-2 Installation
5150 Service Aggregation Switch Hardware Installation and Start-up Manual
009-3222-001 Standard Revision H
Copyright
©
2012-2015 Ciena
®
Corporation July 2015
Mounting bracket kit for 19” frame (two brackets, four cable supports, four
8-32 x 1/2 length screws used to attach the cable supports to the brackets,
and eight 8-32 x 5/16 length pan head screws used to attach the brackets
to the side of the chassis. See Figure 8-1 on page 8-3.)
If the unit is damaged or if any of the above items are missing, please contact
your sales representative.
Note: Mounting brackets for wall mount, and 23-inch racks are also
available. If they are required for your installation, you need to order these
brackets separately.
You will also need to order:
Power supplies (2 DC power supplies)
Power cables
Grounding lug and grounding wire
10 Gigabit Ethernet Option Modules (optional, up to 2 modules can be
installed)
XFPs (for the 10 Gigabit ports on the Ethernet Option Modules, 2 or 4
XFPs can be installed)
SFPs for the 100/1000 Mbps ports (up to 48 ports)
Faceplate cabling
Required Tools and Supplies
For rack mount installations you will also require the following tools:
Phillips #2 screwdriver
Digital Milli-Ohm meter
Rack screws (4 per device)
Cable ties / cord retainers — to secure ground, power and interface
cabling
Wire-strippers (for DC power cable)
Fork terminal spade lugs (3 per DC power supply) — to install power
cabling to a DC system
Power wire (14 AWG) — to install power cabling to a DC system
Note: Table 2-2 on page 2-9 provides a summary of the DC lugs that are
recommended for use with the 5150.