Installation
The safety measure 600 mm behind the granulator hopper, when the hopper is opened checked.
The cutter housing stands horizontally and the stands all machine shoes takes up load.
The granulator have been cleaned from anti-rust oil.
The screws tightening torque to the fixed knife no. 1 (rear) have been checked . . . . . . . . . . . Nm.
The screws tightening torque to the fixed knife no. 2 (front) have been checked . . . . . . . . . . . Nm.
The screws tightening torque to the rotating knives have been checked . . . . . . . . . . . Nm.
The screws tightening torque to the fixed knife no. 3 have been checked . . . . . . . . . . . Nm.
The screws tightening torque to the fixed knife no. 4 have been checked . . . . . . . . . . . Nm.
The screws tightening torque to the fixed knife no. 5 have been checked . . . . . . . . . . . Nm.
Knife clearance checked, knife clearance at the knives outer sides . . . . . . . . . . . and the knives center. . . . . . . . . . . .
The screws tightening torque which fastening the hopper have been checked.
Oil level in worm gear to the roll feeder checked.
Electrical connection
Voltage connection checked . . . . . . . . . . . . Voltage. . . . . . . . . . . . . . .Hz.
Size of fuse controlled 1-phase . . . . . . . . . . . . .A. 3-phase 3 x . . . . . . . . . . . . . A.
The phase sequence of the mains checked.
The granulator have been connected to right-hand field phase sequence.
At least one emergency stop knob is always within reach of the operator inside the working range of the granulator.
The granulator have been on installation fitted with additional . . . . . . . . . . . . . emergency stops.
The rotation direction of the granulator motor have been checked.
The rotation direction of the blower motor have been checked.
The direction of the band conveyor have been checked.
Band conveyor, the band position on rollers have been checked.
The direction of the roll feeder have been checked.
Optional equipment, direction, function and connection have been checked.
The machine have been installed as per section 5 in this instruction manual by:
Date: . . . ./ . . . .20 . . . .Name: . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Responsible and qualified electrician: Name: . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .