Mechanical Installation
18 / 135
3.4.2 Lifting Instruction
Lift the PCS to the height that its bottom is aligned with the rail bracket so that it can
be placed onto the rail bracket smoothly. This operation can be achieved by the
following three lifting options shown below.
Manual lifting: at least three people are needed to properly lift and support
from the base surface (see figure 3-7);
Figure 3-7 Manual lifting from the base surface
Rope lifting: Operate as following steps.
(1) Screw two M10 eyebolts (non-standard) in two opposite sides of the
PCS.
Figure 3-8 Screw two M10 eyebolts