EasyManua.ls Logo

CPS SCA Series - Commissioning Steps

Default Icon
164 pages
Print Icon
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Loading...
69
5.4 Commissioning Steps
Complete the list above before commissioning the inverter as follows:
1. Turn on the AC circuit breaker.
2. Turn “ON” the external DC switch(s)/circuit breaker(s). Skip these two
steps if there are no switches or circuit breakers.
3. Switch the Inverter’s DC Switch to the “ON” position. When the energy
supplied by the PV array is sufficient, the LCD screen of inverter will light
up. The inverter will then start up with the message “sys checking”.
When the inverter completes Initialization”, the LCD will show the screen as
Figure 5-1 below.
Chint Power System
Initialization
Figure 5-1 System Initialization Logo
4. Setting Language. Press ENT to access the main menu, select Setting
and press ENT. The password is “1111”, using the arrow keys enter the
password and press ENT to access the next submenu. Select System
Parameters, press ENT. Scroll to Setting Language, press ENT. Then
select the desired language and press ENT.

Table of Contents

Related product manuals