Transport - 110 JT100/JT100 All Terrain Operator’s Manual
Lift
Lift
This machine is not configured for lifting. If the machine must be lifted, load machine into a container or
onto a platform appropriate for lifting. See “Specifications” on page 247 for weight of machine.
Pipe Box Lifting Procedure
Pipe box lifting points are identified by lifting decals. Lifting at other points is
unsafe and can damage machinery.
Pipe Box
Use optional onboard driver/loader attachment (see Remove/Install Pipe Box” on page 144) or crane
capable of supporting the equipment's size and weight. See “Specifications” on page 247 or measure and
weigh equipment before lifting.