Removal and Replacement Procedures (RRPs)
Note: The ED-DCX-4S-B packaging does not incorporate wood pallet
and pallet brackets. The chassis sits on top of plastic shipping tray.
4. Use a pallet jack or other assisted lift to transport the new chassis
to the installation area. Doorways must be wider than 91 cm (36
in.) to accommodate the chassis on the pallet.
5. Use a lift to raise the chassis to the correct level. If installing the
chassis in a cabinet, follow the instructions provided with the rail
kit.
Installing components into the new chassis
Note: Follow ESD precautions (“ESD precautions”).
1. Replace the WWN bezel (logo plate) and WWN cards (“RRP:
WWN card”).
2. Replace the blower assemblies (“RRP: Blower assembly”).
3. Replace the power supplies or filler panels (“RRP: Power
supply”).
4. Replace the control processor blades (CP8) (“RRP: Control
processor blade (CP8)”).
5. Replace the core switch blades (CR4S-8) (“RRP: Core switch blade
(CR4S-8)”).
6. If ICL cables are not used, insert EMI plugs in the ICL sockets in
the core switch blades (CR4S-8).
7. Replace the port blades or filler panels (“RRP: Port, application,
and encryption blades” and “RRP: Blade filler panel”).
8. Replace the cable management fingers (“RRP: Vertical cable
management fingers”).
9. Connect the power cords to the power supplies and the power
outlets.
10. Replace the chassis door (“RRP: Chassis door”).
11. Power-on the ED-DCX-4S-B (“Connecting a serial cable between
ED-DCX-4S-B and host”).