Verifying the functionality of the circuit
The purpose of verifying the circuit's functionality is to ensure the circuit can detect faults.
1. Connect one of the loops SH terminals to the ground.
2. Verify that the fire panel correctly reports the fault
3. Remove any connection points previously made.
Figure 16: Control panel and 38Ah Batteries metal box connection (accessory item)
1
Nuts on Control Panel
2
Nuts on 38Ah Batteries cabinet
3
38Ah Batteries cabinet (Accessory item)
4
38Ah Batteries
5
Thermal probe
6
Holes for cabinet mounting
7
Connector for Thermal probe
connections