U Fit the cable ducts to the pre-cut holes on the insulating side panels
with self-tapping screws
The position of the individual cable ducts is indicated by the holes
which are various distances apart.
Use self-tapping screws with broad heads!
The vertical cable duct below the switch cabinet must be cut out
horizontally (connection to horizontal duct)
U Fit the switch cabinet to the bracket and lay cable
U After laying the cable, put on the duct covers
3.3.16 Final tests
U Check that all screw connections are tightened
U Check that all the openings of the boiler body are sealed and
professionally closed