INSTALLATION - 2
2.9 INSULATION
WARNING
After the appropriate system tests have been satisfactorily completed, all hot pipework and vessels
must be adequately insulated with material suited to the temperature and application to prevent both

!
Note: It is recommended that for inspection and maintenance, pumps, anges, valves and ttings be left
uninsulated but suitably shielded for safety.
Adhere to the following:
1. Return tanks, surge tanks and deaerators should be insulated. Insulation should be chosen
withcaresuchthattheuidinthetanksdoesnotexceedthemaximumoperatingtemperature
of the pump.
2. Blowdown vessels should not be insulated.
3. Equipment should be insulated with material suitable for the application and temperatures
expected.
2.10 
Upon completion of the installation, adhere to the following for system piping testing:
1. Perform a pneumatic test not exceeding 15 psig.
2. Perform leak spray tests at all welds and joints to ensure that the system is free from leaks.