COMMISSIONING - 3
3.4 CLEANING STEAM LINES AND PRESSURE VESSELS
Duringtherstweekofboileroperation,cleanalloilanddirtfromtheboiler,thesteamlineand
condensate return line.
1. Disconnect the condensate return pipe adjacent to the condensate return tank.
2. Directthereturnstoaoordrainorothersafedischargepointandmakesafe.
3. Leaveinthispositionforoneweektoallowallimpuritiestoushthrough.
4. Drain the boiler completely each day.
5. Aftertheweekiscompleted,drainandushthecondensatereturntank,removingall
installation sediment. Reconnect the condensate return pipe to the condensate return tank.