¾To test Cellular Communication:
1. Contact the central monitoring station to inform them that you are testing the system.
2. Install and activate the SuperBus 2000 Cellular Backup Module.
3. Verify or change the following CS PHONE 1 panel option settings.
Note
If the current settings do not
match the test settings,
record the current settings
(Table 13), so that they can
be restored when this test is
complete.
4. Disconnect the phone line by unplugging the Db-8 cord from the RL-31X Jack.
5. Initiate a phone test (8 + System Master Code + 2).
6. The phone test attempt should fail via the phone line within 5 minutes. The panel will emit a
long low tone (and speak “phone failure 1” if so equipped).
7. Wait for the phone test to succeed via the cell backup. The panel should emit a short high
tone (and speak “phone test ok” if so equipped).
8. Verify the CS report.
9. If success does not occur, verify that the signal strength (RSSI) shown on the Cellular
Backup Module is acceptable and repeat steps 5-8.
10. Restore previous CS PHONE 1 settings if needed.
Table 13: Current Phone Settings
CS PHONE 1 Option Test Setting Previous Setting
PHONE NUMBER Central station phone number
HIGH LEVEL RPTS ON
BACKUP OFF*
CELLULAR BACKUP ON
* Can be set to ON if no CS PHONE 2 PHONE NUMBER is programmed.