ActionStep
Insert the assembled pH electrode into the pH flow cell and fasten the nut.
Make sure that the electrode is tightened correctly to prevent leakage.
5
Connect the monitor cable to the electrode.6
Connect the reference electrode to the grounding wire connected to the pH
cell.
7
UV monitor
The UNICORN instruction Monitors:AutoZeroUV can be used to set the relative AU to
zero.
The Monitors:Wavelength instruction can be used to set wavelength(s).
One to three wavelengths (UV1, UV2 and UV3) can be set within the range 190 to 700
nm for UV-900 monitors.
The wavelength can be set to 215, 260, 280 (default), 405 or 546 nm for UVis-920 monitors
by changing filters in the monitor.
The UNICORN instruction is used for method documentation only.
Note:
116 ÄKTAprocess Operating Instructions 29-0252-49 AA
5 Operation
5.1 Prepare the system
5.1.2 Prepare system components

Table of Contents

Other manuals for GE AKTAprocess

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the GE AKTAprocess and is the answer not in the manual?

GE AKTAprocess Specifications

General IconGeneral
BrandGE
ModelAKTAprocess
CategoryLaboratory Equipment
LanguageEnglish

Related product manuals