ASSEMBLY AND ANCHORING
6-10 MS 3000 • 9095-032A
6.5 Anchoring the mast
If work must be stopped, always
complete the current phase
before stopping. Tighten all the
bolts for the latest fixture and
secure the main switch so that
the mast climbing work platform
cannot be operated.
Before starting to fix any
anchors, ensure that the
chassis is level.
The wall must be of such a
quality that it can accept the
forces applied to it via the
anchors.
The platform extensions and
the anchors must not come into
contact during raising and
lowering.
While a mast element is being
mounted, the emergency stop
switch must be activated.
The anchor forces must be
approved by the owner or the
person responsible for the
building to which the machine
will be anchored.
1. Check that each mast is vertical
with a spirit level at least one metre
long. Recheck as each anchor is
secured.
2. The mast must be anchored to the
building at the distances specified in
chapter 1.
3. The anchors consist of horizontal
anchor tubes with a stretcher
arrangement, mast couplings and a
wall plate.