116
Installing a secondary riser cage
9. Connect the cables.
10. Install the access panel.
11. Slide the server into the rack.
12. Connect each power cord to the server.
13. Connect each power cord to the power source.
14. Power up the server.
The installation is complete.
Installing a secondary riser cage
Prerequisites
Before you perform this procedure, make sure that you have the following items available:
The components included with the hardware option kit
T-10 Torx screwdriver
Procedure
1. Observe the following alert:
CAUTION: To prevent damage to the server or expansion boards, power down the server and
remove all AC power cords before removing or installing the PCI riser cage.
2. Power down the server.
3. Remove all power:

Table of Contents

Related product manuals