Installing tertiary risers
11. Install the access panel.
12. Slide the server into the rack.
13. Connect each power cord to the server.
14. Connect each power cord to the power source.
15. Power up the server.
The installation is complete.
Installing tertiary risers
Prerequisites
Before you perform this procedure, make sure that you have the following items available:
The components included with the hardware option kit
T-10 Torx screwdriver
A tertiary riser cage is required to install this option.
Procedure
1. Power down the server.
2. Do one of the following:
Disconnect each power cord from the power source.
Disconnect each power cord from the server.
3. Do one of the following: