Revision 4.0 ST 700 Series HART/DE Option User’s Manual Page 59
7.5.3 Input Calibration Procedure
7.5.3.1 Correct the Input at Zero
1. Start the MC Toolkit application. Establish communication between the Transmitter and the
MC Toolkit.
2. From the DE MAIN MENU, click Configure to open the DE CONFIGURE display.
3. From the DE CONFIGURE display:
a. Use the PV Units drop-down list to click the appropriate engineering units.
b. Use the keyboard to enter the desired LRV and URV values.
c. Click the Send button to copy the newly entered values to the Transmitter. When the
copy operation is complete, Send will be displayed in half-intensity.
4. Click the Back button to go to the DE MAIN MENU; then click the Calibration button. The
CALIBRATION box will be displayed.
5. Click the Back button to go to the DE MAIN MENU; then click the Calibration button. The
CALIBRATION box will be displayed.