39 
Do not install or remove power cables when the power is on. To avoid human 
injuries, power off the cabinet before performing the operations. 
Upper cable tray 
PGND cable (green and yellow) 
M8 screw 
BGND (black) 
RTN(+) 
–48 V power cable (blue) NEG(-) 
Route the power cables and the PGND cables on the upper cable tray. Connect the PGND cables to the 
ground screws on the top of the cabinet. Route the power cables through the cable hole on the top of the 
cabinet, and then route the power cables to the wiring terminal of the DC power distribution box. 
 
Plug the two-hole OT terminals of the power cables, from top downwards, with the fluted sides facing the front 
side of the cabinet, into the wiring terminals marked with RTN(+) and NEG(-) respectively on the DC power 
distribution box. 
Install OT terminals correctly according to the wiring terminal labels on the plastic 
cover of the DC power distribution box. 
Installing and Routing Power Cables and PGND Cables - Overhead  
Cabling 
d 
Route and bind power cables, signal cables, and optical fibers separately with an interval of more than 3 cm 
between them. For the power cables, first install PGND cables, connect BGND cables to RTN(+), and then 
connect –48 V power cables to NEG(-). 
TN51PDU 
Phillips screwdriver 
Adjustable wrench 
NOTE 
CAUTION 
DANGER 
• Installing and Routing Power Cables and PGND Cables – Overhead Cabling (TN51PDU)