EasyManua.ls Logo

Inovance MD500-PLUS Series - Page 108

Inovance MD500-PLUS Series
173 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Loading...
Mechanical Installation (T13 Models)
‑107‑
Table 6–1 Checklist of Mechanical Installation
Item Action
Compliant
Checked
1
Check the anti‑inclination label.
2
Check that the packing box is intact and free of
damage and damp.
3
Check that the load‑bearing capacity of the
floor and the environment meet the
installation requirements. For details, see "
6.3
Requirements on Ground Flatness
"
on page
102
and "
1.2.1 Environment
"
on page 16
.
4
Check that the ceiling height meets the
minimum requirements (smooth ventilation).
Ensure sufficient space for unobstructed air
supply and exhaust. Reserve sufficient space
for safe passing with the cabinet door open.
For details, see "
1.2.2 Clearances
"
on page 17
.
5
Upon unpacking, check that the cabinet
enclosure is free of deformation, paint peeling
off, and cracking, and that there is no water
stain in the cabinet.
6
Check that the accessories (user guide and
options) in the cabinet are complete.
7
Remove the wooden pallet before placing the
cabinet at the final installation site. For details,
see "
3.4 Unpacking
"
on page 57
.
8
Firmly attach the cabinet to the fixing points
provided.
9
Install all contact protective devices
(protection plates) inside and outside the
cabinet before commissioning.

Table of Contents

Other manuals for Inovance MD500-PLUS Series

Related product manuals