Unpacking Inspection
‑74‑
Figure 3‑12 Lifting the AC drive
2. Roll up the lifting rope slowly with a crane. After the lifting rope is fully stressed, lift
the drive up.
3. Lower the drive down slowly, with a pause at a certain height midway, then
continue until the drive reaches the ground or mounting surface. Finally, install the
drive to the control cabinet.
T10 to T12 Models
To lift T10 to T12 models, do as follows:
1. Hook the lifting lugs at the top of the drive and the lifting holes at the bottom of the
drive, take out the AC drive from the packing box, and lay it flat on the floor.
Ensure that there is no stress on the positive and negative bus terminals.