70
No. Activity Inspection at
every annual
service
Maintenance
must be carried
out at regularly
1 Isolate the boiler from the fuse spur and make safe (ref TB118) check
the correct 3amp fuse fitted.
2 Carry out inspection of boiler for dust and dirt and clean where
necessary.
3 Visually inspect the front plate and heat exchange for signs of
damage. If damage is evident proceed to column 2.
4 Check the gas inlet pressure on HIGH rate (DHW mode).
5 Check combustion by measuring CO, CO
2
. If the values are outside the
tolerances then proceed to a full service in column 2.
6 Close the gas isolation valve.
7 Isolate flow and return valves and drain boiler via the drain o on
the return. Check the charge in the expansion vessel. Recharge if
necessary.
8 Remove the front plate and clean the inside of the heat exchanger.
9 Check the front plate seal and replace the seal if damaged or the seal
is 3 years old..
10 Check the burner and burner seal.
11 Check the ignition pin.
12 Check the condensate trap, clean and fill.
13 Open the isolation valves on flow and return and refill the water in the
boiler to 1.2 bar via the filling loop.
14 Open the gas isolation valve, reconnect the power to the boiler via
fuse spur.
15 Check visually the ignition and burner performance.
16 Check the boiler for leaks of any kind (gas, flue gas, water,
condensate) rectify if necessary.
17 Recheck the CO,CO
2
and adjust if necessary, adjust CO
2
only LOW fire.
18 Complete the Benchmark Service Record on the back pages of the
Installation manual.
10.4 Checklist