Table 19: Site Preparation Checklist (continued)
DatePerformed ByFor More InformationItem or Task
“Rack Requirements for EX3300
Switches” on page 47
“Cabinet Requirements for EX3300
Switches” on page 48
Verify that your rack or cabinet meets the
minimum requirements for the installation of
the switch.
“Clearance Requirements for Airflow
and Hardware Maintenance for
EX3300 Switches” on page 50
Plan rack or cabinet location, including required
space clearances.
Secure the rack or cabinet to the floor and
building structure.
Wall
“Requirements for Mounting an
EX3300 Switch on a Desktop or Wall”
on page 50
Verify that the wall meets the minimum
requirements for the installation of the switch.
“Clearance Requirements for Airflow
and Hardware Maintenance for
EX3300 Switches” on page 50
Verify that there is appropriate clearance in your
selected location.
Cables
Acquire cables and connectors:
•
Determine the number of cables needed
based on your planned configuration.
•
Review the maximum distance allowed for
each cable. Choose the length of cablebased
on the distance between the hardware
components being connected.
Plan the cable routing and management.
Related
Documentation
General Safety Guidelines and Warnings on page 133•
• General Site Guidelines on page 42
• Installing and Connecting an EX3300 Switch on page 65
• Mounting an EX3300 Switch on page 68
General Site Guidelines
This topic applies to hardware devices in the EX Series product family, which includes
switches and the XRE200 External Routing Engine.
This topic also applies to hardware devices in the QFX Series.
Copyright © 2011, Juniper Networks, Inc.42
Complete Hardware Guide for EX3300 Ethernet Switches