11.11 Rotor Operation (With Electric Single-Rotor Lifting Mechanism Design)
Pos: 29.58 /BA/Bedienun g /Schwader/Schwaden/ Kreiselbetriebe bei Ausführung elektr ische Einkreisela ushebung_SW900# @ 161\mod_1 365663793228_78.doc x @ 1415983 @ 22 @ 1
SW700087
2
5
3
1
4
SW9000032
Fig. 45
Single-Rotor Operation with Right Rotor
To swath just with the right rotor, proceed as follows:
• Move the rotor arms to the working position.
• Move switch (5) to position (I).
• Activate the single-acting control unit to lift the left rotor into headland position.
Twin-Rotor-Operation
To swath with both rotors, proceed as follows:
• Move the rotor arms to the working position.
• Bring switch (5) to position (II).
• Move the single-acting control unit to position (“Lowering / Float Position”).
Single-Rotor Operation with Left Rotor
To swath just with the left rotor, proceed as follows:
• Move the rotor arms to the working position.
• Bring switch (5) to position (III).
• Activate the single-acting control unit to lift the right rotor into headland position.