Configuring Battery Settings
0TSet the UPS for the number of EBPs installed.
0TTo ensure maximum battery runtime, configure the UPS for the correct
0Tnumber of EBPs, refer to Table 8 for the appropriate setting of battery numbers and type.
Use the up and down scroll keys to select the number of battery strings according to your
UPS configuration:
0TTable 8 Battery number Configuration
CAUTION
0T● The following process must be performed if the UPS is connected with generator.
0T● First, turn on the generator, after it runs stably connect output power of the
generator to UPS input terminal, then turn on the UPS. After the UPS is turned on,
please connect load one by one.
0T● It is recommended that the generator capacity is as twice as the UPS rated capacity.
0T● You had better not use the ECO mode when the quality of the input AC mains is not
good.