Chapter 8. Installation and Testing Operation
8-5
8.1.5 Preparations during testing operation of Rnet I/F module
This explains contents to be checked before testing operation of Rnet I/F communication module.
1) Communication module to be mounted in PLC
Items to be checked
Contents
Mounting check of
Base module
- Does using voltage of power module comply with specifications of power module?
- Is battery of CPU module connected?
-
Is mounting of all base modules perfect?
Ö See product manual according to each PLC type.
Connection status of
Communication cable
– Is connection status of communication cable perfect?
– Is connection type of each cable open loop?
Module mounting
- Is mounting status of communication module which is mounted in basic base perfect?
Switch checking
– Is the status of mode switch On-line(switch value is 0)?
– Is station No. switch correctly set?
– Is master station No. switch correctly set? (for slave module)
– Is output option switch correctly set when communication is cut off?
(for slave module)