363-208-011, Appendix 1
NJ00675A-2 Dual Power Feed Unit Installation Procedure
Issue 1 November 1998 1-3
during the procedure. Nonetheless this procedure should be scheduled
during a low usage maintenance period.
Procedural Risk Assessment (DPFU added to an
in-service system)
Rating:
MEDIUM Installing the DPFU in an in-service system constitutes a MEDIUM
procedural risk rating, since there is a potential for a service interruption
to the end customer, if any procedural deviations or procedure specific
equipment failures occur during the procedure. This procedure should be
scheduled during a low usage maintenance period.
Equipment
Equipment List
The following equipment, apparatus, and tools are required to perform this
Modification Implementation Procedure.
NOTES:
Code Comcode Qty Note Description
NJ00675A-2, L1 601869118 1 Dual Power Feed Unit
NE00675-31, G1 1 R Cable Assembly (on DPFU)
NE00675-31, G2 1 R Cable Assembly (PIU to DPFU)
NE00675-31, G3 1 R Cable Assembly (DPFU to GRD)
4 R Mounting Screws
4 R 6 Gauge Crimp Terminals
1 R MIP 363-208-501 (Instructions)
1 I Volt-Ohmmeter
1 I Crimping Tool (6 Gauge)