4 Commissioning
BU 0155 en-3520 57
Switch-off mode 3
DIP3/4: ON/OFF
or
P108 = 2
(Factory setting)
Switch on
(Set enable)
1. P2 and P210 determine the starting voltage
(starting torque) that is applied to the motor.
2. The brake opens.
3. P3 and P102 determine the duration for which
the voltage is continuously increased until the
full voltage (100 %) is reached.
Switch off
(Cancellation of
release)
1. The motor is switched off immediately
(voltage "0 %") and runs down to a standstill.
2. The brake is applied when the voltage
reaches "0 %" or after P107 has elapsed.
Switch-off mode 4
DIP3/4: ON/ON
or
P108 = 3
Switch on
(Set enable)
1. P2 and P210 determine the starting voltage
(starting torque) that is applied to the motor.
2. The brake opens.
3. P3 and P102 determine the duration for which
the voltage is continuously increased until the
full voltage (100 %) is reached.
Switch off
(Cancellation of
release)
1. The motor is switched off immediately
(voltage "0 %") and runs down to a standstill.
2. P3 and P103 determine the duration of the
delay, during which the brake is not yet
applied.
3. The brake is applied.