Chapter 5 Multiservice Switch 7460 installation 61
Multiservice Switch 7400 Hardware Installation, Maintenance, and Upgrade 6.1S2
Figure 12
Multiservice Switch 7460 installation task flow: part 2
Task flow navigation
The following references are listed alphabetically:
• “FP addition” (page 151)
• “Grounding a dc-powered Multiservice Switch 7460” (page 229)
• “Installing a control processor” (page 254)
• “Installing a cable management bracket on a Multiservice Switch 7460”
(page 251)
• “Installing a cooling unit into a Multiservice Switch 7460” (page 257)
• “Installing a power supply in a Multiservice Switch 7460” (page 296)
• “Installing a power supply filler in a Multiservice Switch 7460”
(page 292)
• “Installing a Multiservice Switch 7460 shelf assembly” (page 282)
• “Installing a rack-mounted alarm panel / power and alarm panel”
(page 304)
• “Installing dc power cables onto a Multiservice Switch 7460” (page 339)
• “Installing ferrite beads onto dc power cables” (page 346)
• “Installing FP cables” (page 349)
• “Powering up a Multiservice Switch 7460” (page 397)
Yes
No
Add another
FP?
Powering up a
Multiservice
Switch 7460
A
End
FP
addition
PP_TASK_1110
For procedure page
numbers, see
Task flow navigation
below