5-2
CHAPTER 5 Periodic Inspection
2 Precautions
(1) Periodic inspection must be performed by or in the presence of personnel
who have received the Robot Training given by OMRON or OMRON
dealers.
(2) Do not attempt any inspection, adjustment, repair and parts replacement
not described in this manual. This work requires specialized technical
knowledge and skill, and may also involve work hazards.
(3) When inspection is required inside the safeguard enclosure, always turn off
the controller and also the external switch board.
(4) If the inspection or maintenance procedure calls for operation of the robot,
stay outside the safeguard enclosure.
(5) Place a sign indicating the robot is being inspected, to keep others from
operating the controller switch, programming box or operation panel.
(6) Use only the lubricants specied by OMRON or OMRON dealers.
(7) To check the operation after inspection, refer to6 Trial operationin Chapter 1.
For precautions on handling the controller, refer to the “OMRON Robot
Controller Users Manual”.
WARNING
WHEN YOU NEED TO TOUCH THE TERMINALS OR CONNECTORS ON
THE OUTSIDE OF THE CONTROLLER DURING INSPECTION, ALWAYS
FIRST TURN OFF THE CONTROLLER POWER SWITCH AND ALSO THE
POWER SOURCE IN ORDER TO PREVENT POSSIBLE ELECTRICAL
SHOCK.
NEVER TOUCH ANY INTERNAL PARTS OF THE CONTROLLER.

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Omron SCARA R6Y-XC Series and is the answer not in the manual?

Omron SCARA R6Y-XC Series Specifications

General IconGeneral
BrandOmron
ModelSCARA R6Y-XC Series
CategoryRobotics
LanguageEnglish

Related product manuals