EasyManua.ls Logo

Riello GITRE Series - System Filling and Emptying; Water Quality Requirements; Filling

Riello GITRE Series
52 pages
Print Icon
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Loading...
22
INSTALLATION
2.10 System lling and emptying
GITRÈ boilers require a lling pipe connected to the central
heating circuit return pipe.
Turn the mains power switch OFF and turn the control panel
function selector to (0) before lling or draining the system.
2.10.1 Water quality requirements
The heat transfer uid (water) for the central heating circuit must
conform to the quality parameters given in the following table:
REFERENCE VALUES
pH 6-8
Electrical conductivity less than 200 μS/cm (25°C)
Chlorine ions less than 50 ppm
Sulphuric acid ions less than 50 ppm
Total iron less than 0.3 ppm
Alkalinity M less than 50 ppm
Total hardness less than 35°F
Sulphur ions none
Ammonia ions none
Silicon ions less than 30 ppm
If the hardness of the water exceeds the value specied in the
table, it is mandatory to install a water softening system.
9
Excessive water softening (leading to a total hardness < 15°F)
can cause corrosion in metal parts (pipes and boiler com-
ponents). Keep the electrical conductivity of the water un-
der 200 μS/cm.
0
Do not top up the central heating circuit on a frequent or
continuous basis as this can damage the boiler’s heat ex-
changer. The use of automatic topping up systems should
be avoided for this reason.
2.10.2 Filling
RI
Make sure that the central heating drain cock (1) and
storage cylinder drain cock (2) (GITRÈ B/100 models) are
closed before you start lling the system.
Open the non-return valve (3) (GITRÈ B/100 models only)
to facilitate lling (the slot in the screw must be perpen-
dicular to the direction of ow = horizontal)
GITRÈ
1
GITRÈ B/100
3
2
1

Related product manuals