ASSEMBLY AND INSTALLATION 3
3.2 Assembly
Carry out all assembly work onsite. This includes:
▸ Fitting the flange with tube
▸ Fitting the MCU control unit,
▸ Fitting the optional external purge air unit.
3.2.1 Fitting the flange with tube
Fig. 9: Fitting the flange with tube
WARNING:
▸ Observe the relevant safety regulations as well as the safety notices during
all work: see “Important Information”, page 6
▸ Consider the equipment weight specifications when planning the mounting
brac
kets.
▸ Only carry out assembly work on equipment with hazard potential (hot or
aggr
essive gases, higher internal duct pressure) when the equipment
is at a
stan
dstill.
▸ Take suitable protection measures against possible local hazards or haz-
ards arising from the equipment.
All dimensions specified in this Section are shown in mm.
AA
A
A
> 30
Approx.
1°
Ø 195
Assembly on steel duct
Marking for assembly position
Assembly on brick stack Assembly on thin-walled duct
Junction plate
Duct wall
Anchor plate
Flange with tube
NOTE:
Maximum wall and isolation thickness are derived from the flange tube length
(350 mm or 700 mm) less the distance between flange and stack outer wall,
and stack immersion depth (> 30 mm).