PROFIBUS DP communication module
9.6 PROFIBUS DP commissioning using the GSD file in STEP 7 (example)
3RW44 soft starters
164 Manual, 03/2017, NEB535219502000/RS-AB/008
9.6
PROFIBUS DP commissioning using the GSD file in STEP 7
(example)
9.6.1
Introduction
The following example shows you how to commission the PROFIBUS DP communication
module.
Installation and activation of the PROFIBUS DP communication module (fieldbus
interface)
Configuration with STEP 7 using the GSD file
Integration into the user program
Switching on
Components needed
3RW44 soft starter
3RW49 00-0KC00 communication module
General requirements
You have configured an infeed module with integrated S7 station,
e. g. with CPU315-2 DP.
You are proficient in STEP 7.
The programming device is connected to the DP master.
Software requirements
Table 9- 1 Software requirements for commissioning
Configuration software used
Version
Explanations
STEP 7 From version V5.1+SP2
onwards
You have integrated the GSD file of
the soft starter into STEP 7.
Configuration software for the
other DP master used
You have integrated the GSD file of
the soft starter into the applicable
configuration tool.

Table of Contents

Related product manuals