Service and maintenance
Service life of the fan
46
Siemens AG CM2G5111en
2014-05-16
Service and maintenance
The Power Module primarily consists of maintenance-free, electronic components.
Some of the mechanical parts are wearing parts and have to be replaced at certain
intervals.
The following maintenance procedures essentially arise:
1. Regularly remove dirt and impurities in order to ensure that cooling works
effectively.
2. Regularly check that the fans are working properly.
3. Ensure that the cabinet's ventilation slots are not blocked.
4. Regularly check that the cables and screw terminals are correctly fixed in
place.
5. If necessary, re-tighten the fastenings for the cables and screw terminals.
6. Check the cables and screw terminals regularly for damage.
7. Replace any defective parts immediately.
8. Replace wearing parts which are worn.
The actual maintenance intervals depend on the installation and operating
conditions.
Siemens offers its customers tailo
r
-made maintenance contracts. For more
information, please contact your local Siemens representative.
Service life of the fan
The average service life of fans is 40 000 hours. In practice, the service life may
differ from this value, in particular in dusty environments.
The fan must be replaced in good time in order to ensure that the drive remains
ready for operation.
Replacing the fan
Information about replacing the fan can be found in the following manuals:
Hardware Installation Manual for Power Module PM230 IP55/UL Type 12
(A5E02923635A AA)
Hardware Installation Manual for Power Module PM230 IP20 (A5E03448282A
AA)
The fans are available as spare parts through your local Siemens branch office.
5
5.1

Table of Contents

Other manuals for Siemens G120P

Related product manuals