67
Commissioning
8
8.1
PROFINET IO
8.1.1
Commissioning ET 200AL on PROFINET IO
Introduction
The commissioning of your distributed I/O system depends on the system configuration. The
following procedure describes the commissioning of the ET 200AL distributed I/O system on
an IO controller.
Requirements for the ET 200AL distributed I/O system on the PROFINET IO
Note
Performing tests
You must ensure the safety of your pl
ant. You therefore need to perform a complete
functional test and the necessary safety checks before the final commissioning of a plant.
Also plan the tests to include any possible foreseeable errors. This will allow you to prevent
people or plants from be
ing placed in danger during operation.
Procedure
The following table shows the chapters/documents in which the required actions are
described.
Table 8- 1 Requirements for the ET 200AL distributed I/O system on the PROFINET IO
Step
Procedure
See...
1
Mounting the ET 200AL interface module
Section Mounting (Page 23)
2
Wiring the ET 200AL interface module
Section Connecting (Page 28)
3 Configuring the ET 200AL interface mod-
ule
Section Configuring (Page 47)
4 Turning on the supply voltage for the
ET 200AL interface module
IM 157-1 PN interface module
(
https://support.industry.siemens.com/cs/w
w/en/view/89254863) manual
5 ET 200AL interface module automatically
switches to RUN mode
-
Reference
You can find additional information on assigning the PROFINET IO parameters in the
PROFINET with STEP 7 V14
(https://support.industry.siemens.com/cs/ww/en/view/49948856
) function manual.