Operation
76 REVISION 02 * OPERATION SIMOSEC* 832-6063.0
The three-position-switch of the cable / bus sectionalizer and fuse switch panel is
now closed.
Ö Remove operating lever.
Ö Install padlock at center position of control gate of three-position switch (if desired).
Ö Stow away operating lever.
The three-position switch is protected against unauthorized use, if the control gate is
padlocked.
19.4 Switching the three-position switch to OPEN position
Ö Push control gate of three-position switch to the right and hold.
Ö Insert operating lever (with black grip) onto operating shaft of operating mechanism.
Ö Move operating lever down to the "OPEN" position.

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Siemens SIMOSEC and is the answer not in the manual?

Siemens SIMOSEC Specifications

General IconGeneral
BrandSiemens
ModelSIMOSEC
CategoryPower distribution unit
LanguageEnglish

Related product manuals