It is considered Bus no power when Bus
voltage is lower than dead Bus voltage.
It is considered voltage synchronization
when the voltage difference between
Generator and Bus is lower than
synchronization voltage difference.
It is considered frequency
synchronization when the frequency
difference between Generator and Bus
is less than Check Up Freq but more
than Check Low Freq .
It is considered Check Phase Angle
when the initial phase difference is lower
than synchronization phase difference.
Adjust generator frequency and enable it
greater than Bus frequency.
It is the ID mark of the MSC
communication internet. All the MSC
ID should be unique.
Smaller values represent higher
priorities.
0:500kbps;1:250kbps;
2:125kbps;3:50kbps。
Schedule the load value of other genset
when start on demand.
Schedule the load value of other genset
when start on demand.
Speed rate(%/s) of genset
upload/unload
0:Start All Sets;1:Start Sets as Load
Requires
Action Type:
0:No Action;1:Warn;2:Trip.
MSC Too Few
Modules Action
Type
When the input is active, the controller
will start/stop the genset automatically
according to the running time and the
pre-set balanced running time.
When the controller detects no Sync