- 105 -
No.EX##-OMY0004
21. Appendix E: Checklists
The checklists listed in this section provide support when carrying out the following tasks on the EX245-FPS1/2/3 SI unit:
planning, assembly and electrical installation, startup, parameterization, and validation.
These checklists may be used as planning documentation and/or as verification to ensure the steps in
the specified phases are carried out carefully.
Archive the completed checklists to use as reference for recurring tests.
The checklists do not replace the validation, initial startup, and regular testing performed by qualified personnel.
The following section of a checklist shows an example of a completed checklist.
Device type/equipment identification
System XXX has been
checked for engine
hood production
Key:
Equipment identification:
Enter the device type and/or the equipment identification for the relevant module.
Version:
HW/FW enter the hardware and firmware version of the module as shown on the label on the SI Unit."
For details of the label on the SI Unit, see Section 10.10.
Date:
Enter the date on which you began to fill in this checklist.
Editor:
Enter the name of the editor.
Test engineer:
Enter the name of the test engineer.
Remark:
Enter a remark, if necessary.
Requirement (mandatory):
These requirements must be met for a safety application, in order to complete the relevant phase using the checklist.
Requirement (optional):
These requirements are optional. For points that are not met, please enter an appropriate remark in the relevant field.