8. OPERATING PROCEDURES
NOTE!
Before carrying out any operations on the unit read the Safety standards chapter carefully.
NOTE!
With the stop procedure the load will be disconnected.
NOTE!
Letters indications is refered to the visual diagram at chapter 'Electrical installation'.
8.1. SWITCHING ON
• Connect the input and auxiliary mains to the coupling (A and B).
• Wait until the displays switch on.
• Enter MAIN MENU > COMMANDS > UPS PROCEDURES.
• Select Automatic Start Procedure and press ENTER.
• Carry out the operations indicated on the display.
8.2. SWITCHING OFF
This operation interrupts the power supply to the load The UPS and the battery charger will be shutdown.
• Enter menu MAIN MENU > COMMANDS > UPS PROCEDURES.
• Select Automatic Stop Procedure and press ENTER.
• Carry out the operations indicated on the display. This operation cannot be aborted.
NOTE!
The controlled shutdown of each server connected to the LAN can be managed by shutdown software.
8.3. BYPASS OPERATIONS
SWITCHING ONTO MAINTENANCE BYPASS
This operation creates a direct connection between the UPS input and output, excluding the equipment control part. This operation
is performed in the event of:
- standard maintenance
- serious failure has occurred.
WARNING! LOAD POWERED BY AUXILIARY MAINS!
Your load is exposed to mains disturbances.
• Enter menu MAIN MENU > COMMANDS > UPS PROCEDURES.
• Select ON MAINT. BYPASS and press ENTER.
• Carry out the operations indicated on the display.
SWITCHING ON FROM MAINTENANCE BYPASS
• Connect the input mains to the coupling (A and B).
• Wait until the displays switch on
• Enter MAIN MENU > COMMANDS > UPS PROCEDURES.
• Select Automatic Start Procedure and press ENTER.