8.4. EXTENDED OUT OF SERVICE
When the UPS is deactivated for some time, the batteries must be recharged regularly.
They have to be recharged every three months.
• Check output switch Q70 (output load) into position 0.
• Connect the input and auxiliary mains to the coupling (A and B).
• Wait until the displays switch on.
• Close the external battery breaker/fuses.
• Wait until the batteries are fully charged. Check in the menu MAIN MENU > MEASUREMENT > BATTERIES MEASUREMENT.
• Open the external battery breaker/fuses.
• Disconnect the input and auxiliary mains to the coupling (A and B).
8.5. EMERGENCY SHUTDOWN
NOTE!
This operation interrupts the supply to the output load from both inverters and automatic bypass.
UPS POWER OFF
Put the switches Q70 and Q80 at position 0 (located on the coupling cabinet).
REMOTE UPS POWER OFF
If an external main switch is present, it is possible to interrupt the power supply to the output load using the ADC board. Refer to