5.4.6 Equipment Boom Cable Kit (Brand) (EQB)
Cabling All cabinets within the boom must be pulled by Hospital/Contractor if not already
pulled by boom manufacturer
Conduit Terminated within 18" of the center of the ceiling mount
Power Per boom manufacturer specications
Plumbing Per boom manufacturer specications
Access Panel One (1) 24" x 24" access panel adjacent to suspension
Structural Per boom manufacturer specications
ITEM-ITEM QTY SIZE
EQB – A
2
2"
5.4.7 Anesthesia Boom Cable Kit (Brand) (ANB)
Cabling All cables within the boom must be pulled by Hospital/Contractor if not already
pulled by boom manufacturer
Conduit Terminated within 18" of the center of the ceiling mount
Power Per boom manufacturer specications
Plumbing Per boom manufacturer specications
Access Panel One (1) 24" x 24" access panel adjacent to suspension
Structural Per boom manufacturer specications
ITEM-ITEM QTY SIZE
ANB – A
1
2"
5.4.8 Navigation Arm (NAM)
Conduit Terminated to 10" x 10" x 4" NEMA type 1 box within 18" of the center of the ceiling
mount.
Power No additional power required.
Access Panel One (1) 24" x 24" access panel adjacent to suspension
Structural • Optimal location for center of Navigation camera is 47" above nished oor.
• Stryker preinstall plate is installed per customer structural engineer specs at 4"
above nished ceiling.
• A 21" circular hole centered on Stryker preinstall plate in the nished ceiling is
required for installation. A 24" diameter ceiling cover conceals hole aer suspen-
sion is installed.
• e Contractor/electrician to hardwire Stryker electrical whip during Stryker
installation.
• Load location: X=31", Y=45"
• Maximum deection: 1 degree
ITEM-ITEM QTY SIZE
NAM – A
1
2"