6. Innity Based Conference System (IBC) Rooms
LA
Note All cabling must be provided and pulled by Hospital/Contractor prior to Stryker's
arrival.
IBC's are most oen installed in auditoriums, classrooms, and large conference rooms. e IBC can be
installed in a variety of places. e control system can either sit in a closet or in the back of the room.
A podium is recommend to accommodate the IBC Touch Panel and cable runs to the control system.
6.1 SPI3 Customer Supplied Casework (SCW)
Data Per listed equipment
Back Box Per listed equipment
Power Recommended two (2) - 20 amp circuits:
One (1) circuit for quad outlet behind video router
One (1) circuit for quad outlet behind support equipment
Space
Requirements
Casework must allow for a minimum 2" cable passage between all compo-
nents housed inside.
Section housing video router must have an interior dimension of at least
27.5"W X 31"H X 29"D.
Section housing video router must be vented.
Must allow for direct access to backboxes per requirements listed below.
6.2 IBC Unit with Tower (ICW1)
LA
Dimensions 27.5"W X 65"H X 30"D
Data One (1) Ethernet connection
Back Box One(1) 18"W X 18"H X 4"D (minimum) junction box ush mounted.
Set bottom of the box 9" above nished oor within the footprint of the tower.
Terminate all integration conduits to this junction box.
Hospital/Contractors will provide and pull all cables.
Power One (1) - 20 AMP circuit for quad outlet behind the tower.
6.3 IBC Unit with Stryker Credenza (ICW2)
LA
Data One (1) Ethernet connection
Back Box One(1) 18"W X 18"H X 4"D (minimum) junction box ush mounted.
Set bottom of the box 9" above nished oor within the foot print of the tower.
Terminate all integration conduits to this junction box.
Hospital/Contractor will provide and pull all cables.
Power One (1) - 20 amp circuit for quad outlet behind the tower.
Note Customer/Contractor responsible for receiving and installing Credenza prior to
Stryker installation.