Mechanical Installation
4.1 Inspection Before Installation
4.1.1 Deliverables Inspection
Check whether deliverables are complete against the attached packing list.
4.1.2 Product Inspection
Check whether the container received is the ordered one.
Check the ESS and the internal equipment for any damage.
If any problems are found or there is any question, please contact the forwarding company
or SUNGROW.
Only install the ESS when it is complete and intact.
Before installation, ensure that:
The ESS is in good condition without any damage.
All internal equipment is in good condition without any damage.
4.2 Installation Environment Requirements
4.2.1 Installation Site Requirement
The climate environment and geological conditions, such as stress wave emission and
underground water level, should be fully considered when selecting the installation site.
The environment around the installation site should be dry and well ventilated.
There should be no trees around the installation site to prevent branches or leaves
blown off by heavy winds from blocking the door or air inlet of the energy storage system.
The installation site should be away from areas where toxic and harmful gases are
concentrated, and free from inflammable, explosive and corrosive materials.
The installation site should be far away from residential areas to avoid noises.