26
• Hoist the PCS in a vertical manner. Do not drag or drop it on any surface.
• Suspend the hoisting when the PCS is lifted 300mm from the supporting surface to check
the connection between slings and the container. Continue hoisting only after confirming
a reliable connection.
• Place the PCS lightly and smoothly when it is in place.
• The final location should be firm, level, and well-drained. The PCS is supported by four
bottom fittings on the ground.
The PCS should be hoisted by four top corner fittings as shown in the following figure.
figure 5-2 Hoisting by top fittings
5.3 Foundation
5.3.1 Installation Site Selection
When selecting the installation site, consider at least the following requirements:
• The installation location should be as far as possible away from chemical plants and
salt-affected areas. If it cannot be avoided, the later inspection and maintenance cycle
should be shortened.
5 Mechanical Mounting System Manual