10.4 GLP Calibration Alarm
A new feature of the smartCHEM-Titro is the GLP calibration alarm. The operator can select how
often they wish to be reminded that the instrument requires calibration, and for which parameters
they wish to be reminded.
10.4.1 To set the GLP Calibration Alarm…
1. Select the GLP Calibration Alarm menu (
→
→→
→ F5:GLP →
→→
→ F2:Alarm
).
2. The calibration alarm period can now be selected…
GLP ALARM
F1:Daily F2:1 Week
F3:2 Weeks F4:4 Weeks
>F5:OFF
The arrow indicates the current selection.
Press to be reminded that calibration is due every day.
Press to be reminded that calibration is due every week.
Press to be reminded that calibration is due every 2 weeks.
Press to be reminded that calibration is due every 4 weeks.
Press to switch the GLP Calibration Alarm system off.
Press to quit and retain the current setting.
3. If , , or was pressed above, the smartCHEM-Titro will now allow the operator to
select which parameters will be flagged with a calibration alarm…
Select Channels
F1:pH
F3:Temperature
Press the relevant or function key to select which parameter or parameters you would like
to be flagged with a calibration alarm whenever calibration is due. Note the “
∗
∗∗
∗
” which appears
next to the relevant parameter(s).
Pressing the function key repeatedly adds and removes the “
∗
∗∗
∗
”.
4. Press to exit and save the selection.