67
CHAPTER 14
CHAPTER 14 - CHECK-OUT PROCEDURES
Perform the following check-out procedures
as outlined and check off items as complet-
ed. When procedures are completed, the in-
staller should complete the installation record
in Chapter 15 on page 69.
q Boiler system uid chemistry checked and veried
as outlined in Section 10.1 on page 55..
q Boiler system was completely ushed to remove
any debris/sediment.
q Any automatic air vents placed within the system
are open one full turn.
q Air is purged from the heating zones and boiler sys-
tem piping.
q If applicable, conrm that the burner has been
properly congured for Propane as outlined in Sec-
tion 6.3 on page 29.
q Thermostat circuit wiring checked and veried that
no voltage is present as outlined in Section 10.5 on
page 57.
q Operating Instructions on page 58 were followed
during start-up.
q Combustion levels and ame pattern veried as
outlined in Section 11.3.5 on page 60.
NOTICE
q Measured the rate of input on Natural Gas as out-
lined in Section 11.3.6 on page 61.
q Test high temperature limit as outlined in Section
11.3.7 on page 61.
q Checked the incoming gas pressure to the PRES-
TIGE Solo to ensure a minimum pressure of 5”w.c
during ow conditions to all gas appliances and a
maximum pressure of 13”w.c during non-ow con-
ditions for Natural and Propane.
q Adjusted balancing valves and system limit con-
trols to provide design temperatures to the primary
space heating system.
q In multiple zone applications, adjusted for correct
ow of boiler water to each zone.
q Checked and veried room thermostat(s) function
properly and the thermostat(s) heat anticipator (if
used) was properly set.
q Observed several operating cycles for proper oper-
ation of the PRESTIGE Solo and the system.
q Set the room thermostat(s) to the desired room
temperature.
q Reviewed all instructions shipped with the PRES-
TIGE Solo with the homeowner or maintenance
personnel.
q Completed the Installation Record of Chapter 15
on page 69.
q Ensure all manuals and other documents are re-
turned to the Installation envelope and given to
the owner for safekeeping.

Table of Contents

Other manuals for TriangleTube Instinct Series

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the TriangleTube Instinct Series and is the answer not in the manual?

TriangleTube Instinct Series Specifications

General IconGeneral
BrandTriangleTube
ModelInstinct Series
CategoryBoiler
LanguageEnglish

Related product manuals