7 Commissioning/Switching on
In order to establish start readiness, also establish the start readiness of linked
system components according to their operating instructions!
For initial commissioning or before an extended operating shutdown, back up
the device configuration.
Have the backup made by service technicians or in response to a special service
instruction.
The following table contains significantly shortened steps for commissioning
after an extended downtime.
To switch on the combustion calorimeter again after a short shutdown, some
steps can be omitted:
Right column!