Appendix A
PaX-i Plus / Insight Installation Manual 135
4. Before Installation:
Site Check List
Yes No
Is the room large enough?
At minimum,
with CEPH unit : 2,200 mm x 2,200 mm x 2,600 mm /
87” x 87” x 103.
Without CEPH unit : 2,200 mm x 1,400 mm x 2,600 mm / 87” x
55” x 103”
Is the door entrance wider than 800mm (32”)?
Is a radiation protection plan in place?
Does equipment and PC use same dedicated circuit?
Does the electrical input condition to installation site meet the
MEIGaN requirements?
Is the local Network IP address of clinic 192.168.33.xx?
Is compressor or air conditioner suction located right next to X-
ray Room?
Is the floor flat and level?
Is the carpet on the floor? If so, remove it.
Before Opening Boxes
Yes No
Did delivery company carry and handle with caution?
Did installers take pictures of boxes before opening?
Did installer make sure there are not any suspicious holes or
scratches on the box?
Is the ShockWatch indicator red?
Is the TiltWatch indicator red?