6 Assembly and commissioning
Order number 2467031 | Edition 04/2024 21
6 ASSEMBLY AND COMMISSIONING
6.1 TRAINING OF ASSEMBLY/COMMISSIONING PERSONNEL
The assembly and commissioning personnel must have the technical skills to safely
commission the device.
When assembling, commissioning and carrying out all work, read and follow the
operating manuals and safety regulations for the additionally required system
components.
A skilled person must check to ensure that the device is in a reliable state after it is
assembled and commissioned.
6.2 STORAGE CONDITIONS
Until the point of assembly, the device must be stored in a dry location, free from vibrations
and with a minimum of dust. The device must be stored in closed rooms.
The air temperature at the storage location must be between -20°C and +60°C
(-4°F and+140 °F).
The relative air humidity at the storage location must be between 10 and 95%
(without condensation).
6.3 INSTALLATION CONDITIONS
The air temperature at the installation site must be in a range between 0 and 40 °C; 32 and
104 °F.
The relative air humidity at the installation site must be between 10 and 95%
(without condensation).
6.4 ASSEMBLY OF THE MANUAL SYSTEM
6.4.1 Assembly of the mobile base
The manual system's mobile base is supplied partially assembled for transport reasons.
It
must be assembled as described below.
1. Place transport packaging on a clean, level surface.
2. Carefully open the transport packaging as indicated by the pictograms on the
packaging (fold down the side walls of the box completely).