Chapter5MasterDeviceInstallation
UnplugFan
Plug-inBox
Tounplugfanplug-inboxofZXR108902,performthefollowing
steps.
1.Loosenthecaptivescrewsontheupperandlowersideofthe
fanplug-inboxusingacrossscrewdriver .
2.Catchholdofthehandleofthefanplug-inboxandpullthebox
outforcibly.
Result:Fanplug-inboxofZXR108902hasbeenunplugged.
InstallationofCablingRack
Cablingrackisprovidedforcablinginengineeringinstallationwith
ZXR108912,ZXR8908orZXR108905.Cablingrackincludes
verticalsupporterandhorizontalcableplate.Verticalsupporteris
necessaryandhorizontalcableplateisoptional.
InstallingVerticalSupporter
ZXR108912,ZXR108908andZXR108905adoptthesame
methodtoinstallverticalsupporter .T akeZXR108908foran
exampletointroducehowtoinstallverticalsupporter .
Installverticalsupporterincabinet
Makesurethattheplug-inboxhasbeenpluggedincabinetal-
readybeforeverticalsupporterisinstalled.Keepwaist-round
holesofverticalsupporterandthatofplug-inboxonthesame
line,xtheverticalsupporterincabinetwiththreecrown
screws,fastenthecrownscrews,asshowninFigure77.
CondentialandProprietaryInformationofZTECORPORATION79

Table of Contents

Other manuals for Zte ZXR10 8900 Series

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Zte ZXR10 8900 Series and is the answer not in the manual?

Zte ZXR10 8900 Series Specifications

General IconGeneral
Operating Temperature0°C to 45°C
Storage Temperature-40°C to 70°C
Operating Humidity10% to 90% (non-condensing)
Storage Humidity5% to 95% (non-condensing)
Ports10/100/1000BASE-T
Layer SupportLayer 2 and Layer 3
VLAN Support4K VLANs
QoS8 priority queues per port
ManagementCLI, Web, SNMP, RMON
Power SupplyAC or DC
RedundancyPower supply redundancy, fan redundancy