Aprisa SR+ User Manual 1.11.1
1. Getting Started
This section is an overview of the steps required to commission an Aprisa SR+ radio network in the field:
Ensure that the site preparation is complete:
• Power requirements
• Tower requirements
• Environmental considerations, for example, temperature control
• Mounting space
Connect earthing to the radio.
Confirm that the:
• Antenna is mounted and visually aligned
• Feeder cable is connected to the antenna
• Feeder connections are tightened to recommended level
• Tower earthing is complete
Install lightning protection.
Connect the coaxial jumper cable between the lightning protection and the radio
antenna port.
Connect the power to the radio.